FILMINERA PROJECT
Ongoing Projects
Project Details:
- Indirectly owned by CGA Mining Limited
- Located approximately 7km south of the town of Aroroy on the northern coast of the island of Masbate
- Initial studies (October 2007) show gold production at 206,000 ounces per annum for the next eight years
- Site previously developed and operated by Atlas Consolidated Mining and Development Corporation for 14 years (1980 - 1994)
- Operations was closed due to the forced closure of the Atlas group as a result of falling commodity prices and financial difficulties
- Now the largest operating gold project in the Philippines
Client: SMCC Philippines, Inc.
– A Japanese-owned construction company primarily dealing with general construction, civil engineering, architecture, and industrial plant installation
Location: Taganito, Claver, Surigao del Norte